We would like to keep you up to date on the progress of the re-build of The Lodge and The Lakeside Bar and Grill. 

Week 7 Day 1
There something happening now!
Week 6
Not much progress this week. Lumber has arrived. Back filling is complete. Some prep work out of the way for the framing crew. Framing will start on Tuesday. Things will start to take shape now.
Week 5 Steel
Not much to report this week. Supporting steel was delivered and installed to make ready for framing. Lumber delivery Monday. Framing begins! Onward and Upward!
Week 4 Reconstruction
Foundation Complete! Now the fun begins
Week 3 and a Bit!
Weather slows down process. Foundation is now formed and the final pour scheduled. Steel next week with framing the follownig. Stay Tuned!
Week 2 of Reconstruction
Week 2 saw the footings stripped. The primary foundation was formed and poured. Once the initial foundation was stripped backfilling began.
Week 1 of Reconstruction
Back from a nice Holiday. The excavation was completed, the footings formed and poured. Onward and upward.
For Every Ending There's a New Beginning!
With disposal of the debris Cedar Cove is the beneficiary of a new boat trailer parking area and two new sites A12 and A13!
Dec 16 All Wrapped Up Until the New Year
Frost Protection in place until we get back at it in the New Year
Fire Aftermath
A view of the store and restaurant after the Fire on May 23rd, 2011